No Availability Control for one WBS within Project

$
0
0

Hi All,

 

i have got a requirement, where i need to deactivate availability control for one Fifth level WBS where we have 5 level of hierarchy.

 

fifth level is operational as Business requirement. Client want not to have budget/availability control for one WBS where material procured and inventory managed.

 

below is Project Structure:

 

1TJ-10017Ntwk Business Case1
2 TJ-10017.01Capacity
3  TJ-10017.01.B1SBU1
4   TJ-10017.01.B1.NYNew York
5    TJ-10017.01.B1.NY.P121New Mtl Procurement
5    TJ-10017.01.B1.NY.E121Services
5    TJ-10017.01.B1.NY.C145Existing Inventory
_________________________________________________________________________

Client does not want to budget WBS "New Mtl Procurement" and do not want to restrict for cost of any material PO/inventory.

 

is there any way to exclude any posting to this WBS from Budget Check.

 

Note:SAP do have Exempt Cost Element Functionality but as per Business, they do not want to restrict any Cost Element for budget check.

 

Thanks

Sunil