Quantcast
Channel: SCN : Discussion List - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 2586

Cross Company Code STO process for Q stock with two WBS elements of different company code

$
0
0

Hi,

 

We have business scenario, as follows

 

1. Project is created under one controlling area.

2. WBS element 1 @ level 1 with Company code A001 and plant A001 in China

3. WBS element 2 @ Level 1, with Company code A002 and Plant A002 in America

 

Process as follows : Material components are to be manufactured and assembled in WBS element1 with CC A001 and plant A001 in China. Sales order is created against WBS 2 and we need to deliver stock to customer from WBS 2 CC A002 and plant A002 . WBS element 1 will be supplying plant and WBS 2 will be receiving plant.

 

We want to create a Inter company STO process between WBS2 and  WBS1  with valuated project stock "Q". Tried to implement the standard STO process but it is not working with "Q" Stock. Activated business function LOG_MM_SIT.

 

Also gone through sdn for the solution. Not found any solution.

Request the team to guide the STO process with Project stock.

 

thanks

kishore


Viewing all articles
Browse latest Browse all 2586

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>