Hi,
we need to move project stock for specific material qty from WBE1 to WBE2.
Posting 415 Q we have the result of moved project stock from WBE1 to WBE2
but no change in WBE Actual costs as we find row with value 0- from WBE1 and 0+ to WBE2.
Any suggestion to have material qty AND VALUES moved ?
Actually we use the workaround of cascading 411Q (from project to own) and 412Q (from own to project)
but this is really time expensive and moves material STD cost not actual cost (e.g. PO price).
Thank you for your help.
Silvia