Hi gurus,
My client has one line item in contract(SD) with complete scope of work and we are planning to use milestone billing.
eg 10% after signing of contract
20% after approval of design
65% after Production and so on
PS structure is something like below
WBS 1 Order(L1)
1.1 Engineering(L2)
1.2 Production(L2)
1.2.1 Steel(L3)
1.2.2 Cladding(L3)
1.3 Installation
1.4 indirects
I can achieve revenue planning from CJ42 against each wbs element, how can i achieve actual revenue against these WBS
clients requirement is to see the revenue for each level of WSB , eg actual revenue of steel.
Is it possible to achieve such scenario.
Regards
Raj