Quantcast
Channel: SCN : Discussion List - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 2586

Detailed Costing in Version other than 0

$
0
0

Dear Team,

 

We are using BOS for initial cost estimation during project bidding using ECP Costing model in ECP Cost Version (Say 3).

 

Once Project is awarded, we are creating Project in PS and doing detailed network costing. This costing I would like do in Plan Version 1 (other than 0).

 

Once done, we will compare Version 1 and Version 2 (Cost will be transferred from BOS- ECP to PS Str in Version 2)

 

Out of these 2 version which ever less, we will transfer to Version 0.

 

So, at 1st I would like to know, How we can plan detailed costing in version other than 0 and than How I can transfer from Version 1 or 2 to Version 0.

 

Your inputs will be appreciated.

 

Regards

 

Rajat


Viewing all articles
Browse latest Browse all 2586

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>