Hi All,
In our Scenario, Activities are attached to the Lowest Level WBS in the project Structure. POC for activity is calculated in the activities (Measurement method Plan Estimation and Actual - Degree of processing).
I am getting the POC values of the Activities , but these values are not getting aggregated at the WBS level.
If I Specify Measurement method in WBS, the system calculates the Values based on this Measurement method, independant of the data already avl. in the activities.
As per SAP Help If activities are assigned to the WBS element, the POC should be calculated in the activity. The system uses a suitable weighting to aggregate the POC for the activities in the WBS element.
Can Somebody help me in understanding as why the POC values are not getting aggregated in the WBS, based on the POC of the activities._How can I get the POC at WBS level based on the POC of the activities?_
Warm regards,
Srinivas Potluri