Projects Deleted from QA

$
0
0

Hi,

 

We have a issue in quality environment. We have done the following configuration changes and moved to quality:

1. Edit tick in OPSK.

2. Factory calendar in project profile remove.

3. Factory calendar as mandatory field.

4. Change factory calendar to plants.

5. User field keys in network activities.

6. Person responsible.

7. Applicant number.

8. Planning Elements tick removed from planning profile.

9. Change Network type parameters.

10. Change CO versions.

11. Specify parameters for network scheduling.

12. Handling large projects: dataset selection profile.

 

After moving this; the existing WSB elements are deleted from the quality system but those are still shown in F4 and in standard reports also but on opening them system gives error message that WBS element does not exists.

 

Kindly help in analysing this problem.

 

 

Thanks,

Harsh