Hi PS Gurus,
I have a query regarding RPSCO table.
We created a Service PO and did a partial GR on it. We then checked the "Delivery complete" and "Final Invoice" check boxes. We have a custom program which updates the plan cost to the amount field of an external activity of itsnetwork. However, the table AFVC got updated correctly, but the RPSCO tabe having the Value type 1 (Plan) was still have the service PO's value. We raised a note with SAP as the update is done using the standard BAPI BAPI_NETWORK_MAINTAIN.They are unable to come up with an answer. We even disabled all custom codes for SAP to test on but it did not help either.
We even tried running CJEN tcode and several other programs we searched online to update the Plan cost in RPSCO.
Note: The Actual costs (Value type 4) is getting updated accurately in the table.
Please help as this has Financial impact on our Business.
Please let me know if you require more information.
Thanks,
Minil