How to reverse a deleted reserve
Hello, If I have deleted a reserve (CJ20N), and I wanted to reverse the deletion because I want to use the reserve again, what should I do? I can not find the way. Thank you in advance for your help....
View Articlewhen click WBS basic data tab, I get KI112 error .
Hi Experts, I have a situation here, when i try to open a WBS basic data tab i get a pop up error message "enter a controlling area" -I trid to check the controlling area for the in assignment tab and...
View ArticleRegarding RPSCO table
Hi PS Gurus, I have a query regarding RPSCO table. We created a Service PO and did a partial GR on it. We then checked the "Delivery complete" and "Final Invoice" check boxes. We have a custom program...
View ArticleProject PR Remaining Value Closure
Hi, In the standard SAP solution, if I raise a Service Purchase Requisition (Activity) against my project for e.g. £1000 then create a Purchase Order for £500 using this Purchase Requisition, I am then...
View ArticleCustom Report in Project systems
Dear Experts, I need to develop the below report in SAP, Is this possible or not, If Possible can anyone provide me suggestion to develop. If anyone worked can you share the documents to...
View ArticleHow to Control authorization for users with certain status for level 2 WBS...
Dear All, Is there any standard way or enhancement available to control authorization for users with certain status for WBS Element i.e. for example Pre-requisite: There is only 2 level of project...
View ArticleAll WBS elements should be flagged as Billing Elements
Hi everybody, My client wants to have all WBS elements of projects sholuld be falgged as"Billing Element" irrespective of status( fewprojects are in "created" and few are in "REL" andremaining are in...
View ArticleError Overall budget less than overall release
I want to increases my current budget but system shows error Overall budget less than overall release .Now my question is 1) If I want to increases my budget then what is standard process...
View ArticleProject Coding Mask
Hi all, i have attached screenshot herewith, i want to know that the boxes which i have highlighted in screen shot that check box can my make enable in system Regards,Avinash
View ArticleWhy not all fields dimmed or show in display mode after system status TECO...
Dear All, When Sets the system status TECO or even CLSD all fields for WBS Elements are not goes to Display mode. User can still edit them or change then. The fields are: 1. WBS Element Description,...
View ArticleCost Forecasting in SAP
Dear Experts, In Project Systems - My user wants to update cost forecasting amount for some wbs elements manually for every month in SAP. Can I suggest CJ40 or is there any other t-code to update cost...
View ArticlePO Creation without WBS budget but AVAC activated
Dear Experts, I have activated budget with AVAC for a project, If budget is available in wbs element i can create PO and post direct cost. But for some wbs elements there is no budget and the user...
View ArticleSales Order Link
Hi, While i am trying to enter the line item in sales order i am getting popup asking for WBS element. I dont want this pop up to be triggered rather i need to create sales order first then project...
View ArticleCost updated in CJR2 cannot see in report CJI4
Dear Experts, I updated the below parameters in CJR2(Screenshots Attached) Updated 1000 in "Total plan cost" Fields and saved(Screenshot attached) But this data i cannot see in reports...
View ArticleWBS Original Budget versus Approved Budget
Dear Experts, In a Project, I have original budget of 100 INR for a WBS element, If customer may approve 80 INR or 120 INR. This 100 I can show in CJ30 original budget column now where this approved...
View ArticleAccount Assignment for WBS elements
Dear All, If we have a 5 level of WBS elements in project. and in that first two level we don't want any account assignment, 3rd level onward we want account assignment. Manually we can do in project...
View ArticleDiplay cost at compoment level in CN41N report
Hello Guru's, CN41N report shows the materials but does not show the material costs. Business requirement is to display costs (planned and actual) on material level in single report. Looking at report...
View ArticleCJ20N Error
Hello Friends, We are getting an error for this particular employee on tcode CJ20N main screen "Entry length incorrect". We tried lots of things but nothing is working out. We did debugging on that...
View ArticleAlternative valuation for projects
Hello everyone, We have a multiple ledger set-up, where we copy actual values to a plan version, run distributions and allocations, calculate plan prices for activities and finally run the AVR cockpit....
View ArticleGI Actual Cost-Material Component
Hello Experts, I have maintained movement type 101 for GR, 281 for GI for valuated project stock and Item Category L for creating material component. Actually, my report reflects the planned figures on...
View Article