Current budget value is missing

$
0
0

Dear Colleagues,

 

please advise what could be the reason for the following problem.

 

Transaction CJ31 (display original budget) shows no value for the field 'current budget' for the current fiscal year, but Project Cost Line Items (CJI4) shows, that the value was planned and cancelled several times, but at least it has line item.

 

Besides total for annual values (FY2013 + FY2014) in CJ31 shows the value as FY has budget amount

 

e.g.

 

CJI4 for WBS for FY2014: 300

 

FY2013  Current Budget 100

 

FY2014 Current Budget 0

 

Total for annual values 400

 

Many thanks in advance.

 

Kind regards,

Irina