Actually we are going through SAP project system implementation, i am on client side and i want to confirm whether there is an option in SAP PS that different working calendars be set, like Primavera, where different working calendars are customized in master list and then assigned to relevant activity. Because at some places 5 days working is a practice while at some places 6 days. So each activity has to be assigned relevant calendar based on which it records planned finish date just by giving the duration of activity. Also holidays in a year also vary from place to place. Using just a single working calendar would misguide the planner.
↧