Experts,
I am facing an issue for which your help is required.
One of my user is trying to change the investment program which gives the error -:
" WBS element PR/xxxxxx/xxxxxx is already budgeted or availabilty control is active"
Now my understanding is that in such a case the budget needs to be removed which will undo the user status BUDG and subsequently allow the user to make needfull changes.
I therefore went into IM52 and tried to delete the budgeted figure, upon saving I get an error "Overall budget is negative X - (value)"
Please guide me in the right direction to resolve this issue at the earliest.
PS --> This is a capex scheme .
rgds'