Dear All,
Am back here for the expert suggestions / guidance.
I am facing issue with respect to system not updating the actual cost in network activity / projects posted through time sheet i.e. CATS. I have planned my resource cost through work centre assigned with activity type, formula and cost centre. I have kept the employee master data in place with maintaining the 315 infotype. In CAT2 i am posting the respective time sheet on the particular network activity and am transferring the cost into projects by CAT5, the plan cost is getting updated but actuals are not hitting the projects.
Kindly do the needful and suggest me if am missing something out of the track
Thanks
Praveen Mohanachary