Hi All,
I would like to know how the overhead setting in OKK4 for Projects, especially how to set Administration OH calculation in planning cost.
It shows below automatic calculation OH in Project Planning. In my opinion, in order to get Administration OH the formula below will be used.
Administration OH = Rate X ( Consumption of Semifinished Product + OH Surcharge Material + OH Surcharge Personnel +
Dir. Int. Act. Alloc. Production)
CE | Planning | Rate | |
655300 | Administration overhead rate | 370.41 | 0.2 |
890000 | Consumption of semifinished product | 1,533.88 | |
655110 | Overhead Surcharge - Other Materials | 76.69 | 0.05 |
655200 | Overhead Surcharge - Personnel | 11.5 | 0.05 |
619000 | Dir. Int. Act. Alloc. Production | 230 | |
655400 | Sales overhead rate | 277.82 | 0.15 |
Total | 2,500.30 |
I also have attached the OKK4 setting in IDES.
Appreciate for your explanation.
Cheers,
Nies