Hi Experts,
Is there a way to bypass the activity type set in the Internal tab of a particular activity in CJ20n?
Here's a background of the scenario:.
- In CJ20n, under WBS element 100->Network 10->Activity 1, under the internal tab, the activity type set up is ACT1
- Under person assignment, I have 2 resources assigned Person 1 and Person 2, with the following values:
Person 1 Work: 1.0h Dur. 10D
Person 2 Work: 2.0h Dur. 15D
- In infotype 135, person 1 has a cost element set as ACT2 and person 2 has a cost element ACT3.
- The problem is that when you bring up the Plan/ Actual comparision report (ctrl+F11 in CJ20n), the costs are consolidated for ACT1 and negates the cost elements for Person 1 and Person 2
Is there a way to bypass this and use the individual cost elements set up for person 1 and person 2?