Integration of PS to Ariba APC catalogue

Hi, Has anybody had any experience of connection PS to either Ariba APC or SAP MDM catalogues for purchasing? My customer has managed the punch-out connection to APC, but is having trouble punching...

View Article


Is there a way to bypass activity type/ cost element for CJ20n Activity?

Hi Experts, Is there a way to bypass the activity type set in the Internal tab of a particular activity in CJ20n? Here's a background of the scenario:.- In CJ20n, under WBS element 100->Network...

View Article


WBS is not appearing in CJ03, CN41 etc.

Hi Experts,I'm facing one strange issue. In a project structure, there is a WBS at level 5 (A.00000212.1.2.09.02.B). There is some posting on WBS and status is REL. When we enter project defintion in...

View Article

Transferring of balance stock to other project.

Hi Experts, I have to transfer certain stock to the other project. Please let me know the steps to do that. Regards,Wasim.

View Article

Create project from sales order

Hello Experts, I have a requirement to create project from sales order for real estate client. Can you provide me the configuration steps to achieve the same as I am new in this area and dont have much...

View Article


Multiple PR's generating for same material after MRP

Hi Guru's,As per my business scenario, i am creating project with WBSE, Activities and BOM. By using the reference points, i am transferring the BOM to Project, then executing MRP run. But after MRP...

View Article

SAP Material Master

GuysI am novice in SAP PS  , Need Help can you please advice how to access this information from my  SAP Server , Appreciate your response Assembly Processing 1) Need a List of all materials that are...

View Article

How can i get difference in base plan and actual/current plan for a project

Hi PS Experts, How can i get difference in base plan and actual plan .For example-Project1 is created for 10 days (start and end date difference).Now in between -project is extended/changed for 12 days...

View Article


How to integrate ps with pm module for shut down management

Hi Experts, Please let me now how can i integrate PS and PM module for shutdown management. My requirement is to create a shut down project and assign resources and material .Then want to create a Work...

View Article


Image may be NSFW.
Clik here to view.

Actual Revenue Not Updating in PS Reports

Dear All, Threre are many threads available regarding that issue but none of the thread is not giving me answer.My Problem is that. Sales order is assigned to WBS Element and Plan revenue is coming...

View Article

OPI2, OPI8

Hi, Can you please help to understand the use for value category from OPI2/OPI8? In CJVC we have all cost elements assigned to cost element group and cost element group assigned to value category. What...

View Article

DP91 not showing fixed price SO item

HiI am not sure like this question belongs to SD or PS, any way the issue here is, Fixed price line items are not appearing in the DMR created through DP91. Let me elaborate.. total 3 line item in the...

View Article

Not possible to delete link investment program position from Appropriation...

Dear specialists, We have a problem with deleting a linked investment program position in an appropriation request (IMA3, IMA11 or IMA12).We could edit some of the appr.req.'s but a few give an error....

View Article


CNMASS - Ability to apply custom fields from structure CI_PROJ

Hi, Is there a way to add fields from the Customer Enhancment tab in structures CI_PROJ, CI_PRPS to CNAMSS transaction? thanks,Cathy

View Article

Image may be NSFW.
Clik here to view.

WBS Forecast dates disappears during scheduling after final confirmation

Hi dear Experts.I faced a problem with WBS dates. The system overwrites forecast and basic dates on WBS after final confirmation of attached activities. And start to schedule wbs dates from dates of...

View Article


Wrong planned cost calculation while actual is calculating correct for...

Dear all, I am facing an issue in which when i am doing network costing with work center, activity type, cost center and giving per hour rate in KP26. System is calculating correct actual cost but...

View Article

Image may be NSFW.
Clik here to view.

Create project as released

Hi' We create projects through Assembly Processing. We want the Projects to be created with System Status Released. I can customize that the network is created with status Released, but are there any...

View Article


material availability check not being executed

First of all: I’m an SD consultant with limited knowledge about PS At our current client are we facing an issue with the material availability check in project system orders, created through e.g....

View Article

Result Analysis Reversal

Hi, Does any one know how to reverse Result Analysis of a previous closed Fiscal Year? Client requirement is to reverse Milestone booked last year through customized transaction and not through Sales...

View Article

How can I enter actual percentage of completion in the WBS elements?

Hi all ! I Can not enter Actual percentage of completion in WBS elements...! I have followed these steps in Progress analysis: 1.- In the progress tab of WBS elements I have entered Measurement method...

View Article