Quantcast
Channel: SCN : Discussion List - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 2586

Actual Revenue Not Updating in PS Reports

$
0
0


Dear All,

 

Threre are many threads available regarding that issue but none of the thread is not giving me answer.

My Problem is that. Sales order is assigned to WBS Element and Plan revenue is coming from billing plan via milestones.

But during actual invoicing actual revenue is not updating in my PS reports. Even it is updating in CJI3 in Revenue cost elements.

I have run CJEN and still actual revenue is not coming in project reports.

Please find config screen shots. Cost element category is 11 only.

Invoicing is hiting correct cost element which is 40000060 but why it is not updating in my reports.

please guide me, what is missing?

 

 

Thanks & regards.

Sukhveer.

 

Planning Profile.PNGCJI3.PNG

PlanActual Rev.PNG


Viewing all articles
Browse latest Browse all 2586

Trending Articles