Hi all !

 


I Can not enter Actual percentage of completion in WBS elements...!

 

I have followed these steps in Progress analysis:

 

1.- In the progress tab of WBS elements I have entered Measurement method ESTIMATION for
progress analysis (Plan&Actual).

 

2.- In the WBS element I have estimated PLAN percentage of completion 100% in period 8

 

3.- In the progress tab of network activities, I used ESTIMATION method for Plan and WORK for actual
to calculate the percentage of completion.


4.- I have entered final network confirmations

 

Actual Start date: 08.11.2014
Actual Finish date: 08.15.2014

Remaining work is cero.

 

5.- I run Project analysis to display measurement methods with transaction CNE1
and Progress analysis with transaction CNSE5

 

In Progress analysis the Processing % of work in Network activities is 100% but 0% in the WBS
element

Adj.NAgg.Act. POC (Adjusted non-aggregated actual percentage of completion)is 100% in network activities
POC actual, non-agg.(Non-aggregated actual percentage of completion)is 100% in network activities.

 

Does SAP calculates actual POC?

 

Should I manually enter Actual percentage of completion in the WBS elements?

 

I can not enter percent of completion (actual value) for WBS elements. The field is non editable !

 

Please help !