Hi every one,
I have issues with activity confirmation report.
Issue1: I have confirmed activity 2 to 3 times, system is allowing to confirm more than 100%. I have used workcenter with processing % as 100%.
Issue2: After cancellation of activity, system is showing wrong values in actual processing % values and report is showing wrong.
I have not used any capacity requirements.
I request to tell me the reason and how to correct the issues.