Variable value in Report currency inconsistent
Hi Experts,We are currently facing an issue with the variable value in report currency in actual cost line item reports (cji3).The amount does not seem to be visible for one user id and for the other...
View ArticleCondition Determination in CN33
Hi Experts, I am attempting to build a report that would mimic PO creation process for my client. My issue is that I am unable to find where the conditions are determined for each component being added...
View ArticleMultiple PR's generating for same material after MRP
Hi Guru's,As per my business scenario, i am creating project with WBSE, Activities and BOM. By using the reference points, i am transferring the BOM to Project, then executing MRP run. But after MRP...
View ArticleBAPI in Investment Management
Hello Could you please help me in getting the BAPI to upload 'Budget Distribution' ( IM52 ) in investment management ? I am also looking for a BAPI to load data for transaction IM32 ( Change Original...
View ArticleBudget Translation Customizing
Hi Experts,Share your thoughts & comments on budget translation.Budget is maintained on Project for over all in AUD. When actual cost is captured for current year through a PO with AUD as...
View ArticleHow can i get difference in base plan and actual/current plan for a project
Hi PS Experts, How can i get difference in base plan and actual plan .For example-Project1 is created for 10 days (start and end date difference).Now in between -project is extended/changed for 12 days...
View ArticleSAP PS-Activity cancellation issue
Hi every one, I have issues with activity confirmation report.Issue1: I have confirmed activity 2 to 3 times, system is allowing to confirm more than 100%. I have used workcenter with processing % as...
View ArticleNot possible to delete link investment program position from Appropriation...
Dear specialists, We have a problem with deleting a linked investment program position in an appropriation request (IMA3, IMA11 or IMA12).We could edit some of the appr.req.'s but a few give an error....
View ArticleSAP Allowed To Close WBS When There Is balance
Hi After recent technical upgrade last week, it is happening that when we try to close WBS with balances, SAP gives us warning and allow us to close. Earlier it use to give Error message in Red and...
View ArticleCNMASS - Ability to apply custom fields from structure CI_PROJ
Hi, Is there a way to add fields from the Customer Enhancment tab in structures CI_PROJ, CI_PRPS to CNAMSS transaction? thanks,Cathy
View ArticleSAP PS Summation issue while running reports
There is a issue with the WBS Summation in my ProjectSummation is not coming correct for the report S_ALR_87013558 for old projects .Even after running CJEN also. Please advise me is there any Note is...
View ArticleCJI3 Report View to Users
Hi Gurus, My users were unable to view the CJI3 Values when the cost had been settled, i.e when the values become zero, it gives them an error with No Cost / Revenues. But when i view the CJI3 Report,...
View ArticleHow to set plant to all WBS when creating Project using Copy Standard Project...
HelloI have created standard project with several WBS. Now I want t o create operative project in CJ20N by copying standard project. While copying I want that the system allows me to define the plant...
View ArticleCATS_DA does not display properly
Hi All, Hoping you could assist. We have recently transfered a resource from Cost centre A to cost centre B. After doing the posting (7.00 hours on cc A, and 8.00 hours on cc B), CATS_ZA displays the...
View ArticleReport of material consumed against Project PO WBS
Hi Gurus, I am looking for a report that will help me to track the total material consumed against the PO. Please let me know if there is any Std report or tables information where i can fetch the...
View ArticleDP91 View
HiNeed inputs from PS professionals, especially in DIP area.I am trying explain the current setup, so that you experts can comment on approach too...Acticity 1 (Internal), which have 5 Job codes...
View ArticleSimulation Version not showing Activities in Planning Board
Hello, I transferred an Operative Project to a Simulation Version, it was successful without errors. When I open the simulation version in Project planning board with (planing Board Profile to show...
View ArticleEasy Cost Planning at Network Level
Hi All, I was able to implement ECP at WBS level, but not able to implement at network level. I am using SAP ECC 6.0 EHP 4.I have activated the business function ops_ps_ci_1 and also activated the...
View ArticleDP91 unbilled amount
HiOn DP91 i selected 50% for billing, created DMR and later DM.How do i bill the 50% amount...?? While i retrigger again DP91, system says "No Data was changed"
View ArticleStd. Report that shows PSG linked to WBS (Pdt. hier. defined)
Hi Experts, Is there any standard report that show, which Profit segment is derived and receives settled costs and revenues for a particular WBSE? Our scenario:(1) Billing WBS element is assigned to SO...
View Article