Hi,
I've got existing Network templates set up for various company codes. The std networks are linked to std wbs elements. This creates a full project structure when coping the standard network in CJ20N.
However, on an existing company code and plant, I am creating a network template with std wbs assignment, the point at which the other networks jump to the WBS create screen to replace WBS / Proj numbers etc... is NOT HAPPENING. The system immediately asks for a OPERATIVE WBS to be entered.
This company code specifically requested in the past that that their users only use operative WBS elements. Question: Where is it possible to set this restriction for a specific company code / org unit so the std network ignores the std wbs assignment and requests an operative WBS entry?
Thanks
Kru