Standard Network with Standard WBS not creating the project

$
0
0

Hi,

 

I've got existing Network templates set up for various company codes. The std networks are linked to std wbs elements. This creates a full project structure when coping the standard network in CJ20N.

 

However, on an existing company code and plant, I am creating a network template with std wbs assignment, the point at which the other networks jump to the WBS create screen to replace WBS / Proj numbers etc... is NOT HAPPENING. The system immediately asks for a OPERATIVE WBS to be entered.

 

This company code specifically requested in the past that that their users only use operative WBS elements. Question: Where is it possible to set this restriction for a specific company code / org unit so the std network ignores the std wbs assignment and requests an operative WBS entry?

 

Thanks

Kru