Quantcast
Channel: SCN : Discussion List - SAP Project Systems (SAP PS)
Viewing all 2586 articles
Browse latest View live

Settlement process

$
0
0

Hi All.

 

 

I am doing my first implementation project. Can any one please tell me the settlement process and what information i have to gather from FI/CO consultants.

 

 

Settlement profile

Allocation structure

PA transfer

 

 

 

Thanks

Praveen


Incorrect WBS number determined in SD Contract

$
0
0

Hi,

 

We have configured our system such that when a material is added in the contract, WBS (level 1) gets created for each material in contract. These WBS are then assigned to the main project.

 

I have a contract with a material in line item 10 and its wbs is ABD-Contract no- Line item no (10)

Similarly for material in line item 20 of contract its WBS is ABD-Contract no- line item (20)

 

Both the above WBS has been closed and its current status is CLSD.

 

Now when i try to add a new line item in contract (line item 30), the system is determining the WBS element no. as ABD-contrac no- line item no 20. and the system is giving error as "System status CLSD is active for WBS ABD-Contract no- Line item 20

 

Can anyone tell me why the system is determining the WBS of line item 20 when i try to add new material to line item 30. Ideally the WBS should have been ABD-Contractno - Line item no 30

 

Any inputs on this?

 

Thanks

 

Regards,

Dhwni Patel

Cut Over Stratergy

$
0
0

Dear All,

We are going to fix cut over stratergy for go-live, but i as per requirement, i need to capture all historical costs and revenues (which were inccured in legacy system) into SAP. So i have very much confusion in this regards,kindly help me on this.

 

     Here the challenge is that, we need to calculate the RA (Cost based POC method) values in SAP based on cummulative Costs and Revenues both

Planned and Actuals.

 

I have read some blogs but still i have no clarity on bringing the historical Costs and Revenues into SAP. If any one can explain in detail that will be helpfull for me. Also please guide me how the WIP will be brought into project.

 

 

 

 

So please guide me how to achieve this.

 

 

 

 

Regards,

Rao.

OPI2 : suppress indicator impacts on BU availability controls

$
0
0


Dear experts,

 

We have configured a specific value category RR for revenues CE within OPI1 and we have activated the update option 'suppress' for PS report within OPI2.

 

My question: does the option 'suppress' for revenue's valuation category have any impact on the active budget availability control ?

 

My understanding is that posting to a revenue value category / CE is automatically excluded from the assigned value / availability control.. and the 'suppress' option is only used if you want to exclude them from the PS reports. pls confirm.

 

SAP notes 178837 and 777859 are not clear for me ;-(

 

Thanks and regards,

M Yernaux

SAP PPM and PS for projects involving several plants

$
0
0

Hello,

 

I am investigating the possibility to plan and control the development costs at the company with the SAP PS or PPM. Thus, the goal was having team members booking their labor hours to the projects (Maybe through CATS?), so that project managers could have a detailed and exact overview of the costs of their projects attributed to each person and department. However, since a development project takes place at several sites, with team members in different plants working for it, I have been told that with SAP PS it is not possible to do it because at PS a project would be attributed to one Plant, and therefore people in other plants, from the same company, would not be able to book their labor hours to the projects. Is that really so? Is there a way to bypass this problem? Can different WBSs at the same project be attributed to different plants?

 

Thanks a lot for any help!

 

Gustavo

Consumption (281 movement type)CN25 activity confirmation

$
0
0

Hi,

 

i have created project,network,activity and assigned material component, i run MD51 for MRP planning with reservation and created Purchase order,GRN also.

then i am going to posting CN25 activity consumption this below message i am getting.

 

Confirmation saved (Goods Movements:0 failed :1)

Message No.RU110.

Diagnosis

You have saved the confirmation. In the process, the system has also posted
the the backflush of the components and the automatic goods receipt. This system
issues the message that 0 goods movements were posted successfully and that in
the case of 1 items the posting failed due to an error situation.

 

Procedure

You can postprocess the faulty goods movements by invoking the postprocessing
function from the initial menu for for production orders.

 

Execute function

 

when i click Execute function it goes to COGI tcode.

 

please suggest on this..

regads,

siddu.

IM52 - unable to check in report

$
0
0

Hello,

After doing IM52, the budget gets distributed correctly.But the same is not correctly displayed in reports.I expect if the original budget was for 100 and supplement was for 50 , the reports (project) should show me 150- but it does not so show.Do i need to do something in project reports.

Rgds

 

SRJ

Process to change BOM Quantity after BOM explosion

$
0
0

Hi,

 

I want to what is the process that is normally being followed to change the BOM quantity once BOM has been exploded.

I will clarify my point.

I have attached a finished material to the activity and exploded the BOM manually (edit>component>explode).

Now if I want to change the quantity of the header BOM material from (say) 1 to 2 quantity, then how the BOM quantities will get updated accordingly.

e.g. BOM material A has two components B and C.

one A quantity has BOM ---- B is 2 nos. and C say 3 nos.

So if I change the A quantity to 2 nos. after the BOM is exploded then how the quantity of B will become 2X2 = 4 and C will become 6.

 

What is the process that is normally followed to update the quantity.

 

Abhra.


SAP PS - Copy create new company code in same client

$
0
0

Hi All,

 

I need your expert advice on the below mentioned scenario,

 

Objective -

 

Creating new company code(New business entities - new company) using existing company code in same client. "As is there is" Approach.

 

From Project systems perspective I have checked the following things with the existing process and also new requirements if any,

 

1. List of project profiles (Few company code specific and few don't have company code).

2. No change in the business process in new company code.

3. No new enhancements.

4. There are differeent project types for differents process - which needs to be copied as it is in new company code.

5. ZREPORTS/Interfaces/ZPROGRAMES/Jobs .

6. New company code related naming conventions for PS configurations (Coding mask/ project profiles/Project types,,etc).

 

 

Need your inputs for the below mentioned points,(PS perspective)

 

Assuming that FI team does the copy company code trasnactions.(Creates controlling area and FI Org structure which we use for PS also)

 

1. When copy company code is done which all settings/configurations are created in new company code and which all are not created ?

2. What additional parameters I should take care ?

3. What additional information I should get from business team ?

4. Which is best approach/method for data migration for PS templates and transaction data (open projects) ?

 

I have already refered other treads, I couldnt find much helpfull.

 

http://scn.sap.com/thread/3650518

 

Thanks in advance,

SSP

Resourse allocation to project WBS

$
0
0

SAP Gurus,

 

I am working on a project to replace Primavera with CA PPM for PLC.  Resources will be assigned in CA PPM and sent to SAP via integration interface.  In order for the resources to enter time for a WBS or multiple WBS for different projects, where in SAP should resources be stored?

Resources will need to charge time to projects using CATS.

 

Thanks

Shirley

Export to Excel -CN41N Report

$
0
0

Dear all,

 

How to import CN41N report to Excel?

 

I search out in SCN and other site but answer not found. Is it any other way to import to excel.

 

 

 

 

 

Regards

Amit

Capitalization and Expense on same SAP PS Project

$
0
0

SAP PS Gurus,

 

I have a requirement to show capitalized, expense, R&D, in the same project.  Currently, we have a standard project def with the appropriate settlement profile assigned for each standard project def., because the settlement rules are different for each type of the operations.  How can this be
set up in SAP PS to support this requirement?

 

Thanks

Shirley

DIP: Each WBS in 1 line at the DMR order - how to?

$
0
0

Hi'

 

I hope some of you can help us

 

Our solution:

* Material A is added at Contract i VA41

 

*A project with network and activities is created automatically (assembly processing)

 

*The project are changed to fit each delivery - end up with 2-30 WBS-elements

 

*CATS-confirmations at the network activities are created in CAT2 and transferred to the project through CAT5

 

*DP91 capture CATS-confirmations with activity type A = material A, B = material B and C = material C (material determination)

The DMR contain 1 line item per activity type

 

Now we would like the DMR to have these line items:

 

WBS 1 with activity type A

WBS 1 with activity type B

WBS 1 with activity type C

WBS 2 with activity type A

WBS 2 with activity type B

WBS 2 with activity type C

WBS 3 with activity type A

and so on.

 

How can we solve this issue?

The WBS-elements have different names for each project. We had not succes to create a Set reflecting this.

How can we make the setup resulting in the mentioned DMR line items.

 

I hope for some input.

Thank you in advance

 

Regards

Lone

MIGO Posting not checking AVAC

$
0
0

hello experts,

 

As per Note 46209 no availability control on Goods Receipts.

 

But my question is Goods Receipt can be created only after creation of Purchase order only right ?

while creating PO itself the amount from WBS budget will be assigned for particular PO. then why we need additional amount for Good receipt ?

 

please clear me this point.

 

thanks.

WBS AVAC De-activated through different transactions

$
0
0

Hi Team,

 

As per SAP standard, one is able to change the status of Availability Control (AVAC) within PS through CJBW (deactivate AVAC), CJBV (activate AVAC) and CJBN (reconstruct AVAC). As such we have limited the access to these transaction codes to our PS super users only as they are critical actions.

 

We have found that a few users have been able to deactivate AVAC on a project through the following transactions:

 

FBV0 - Post parked document
FBVB - Post parked document
FV50 - Park General Ledger Account Documents
FV60 - Park Incomming Invoice
IW32 - Change Work Order
ME21N - Create Purchase Order
ME22N - Change Purchase Order
ME54N - Release Purchase Requisition
MIGO_GI - Goods Issues
ML81N - Service Entry Sheet
MR8M - Cancel Invoice

 

The above was identified using table JCDS - status change logs which was executed for WBS element objects when project overspend was investigated. If the above is true, this would cause a situation in that any person who has access to the above would be able to deactivate AVAC on a project.

 

This can not be allowed as all forms of capital governance is lost in that individuals within the the Buying/Procurement/Contract department can override budget controls put in place by the Capital Portfolio department.


We have tried many times to replicate the issue but we have been unsuccessful and after taking this issue to SAP and no assistance being available as we can not provide steps to replicate, we would like to know if anyone else has seen this issue or has had this same issue?


We have subsequently setup a CJBN batch job to execute daily as a preventative measure but this still will not prevent the issue from reoccuring.


Any help or guidance is greatly appreciated.


Thanks a lot.


Syanne


Is it possible to post aganist Network plan revenue and actual revenue

$
0
0

Hi Gurus,

 

can we post the aganist Network plan revenue and actual revenue.

if yes please suggest which scenario we will use this...

 

 

regards,

siddu.

Cut Over Stratergy

$
0
0

Dear All,

We are going to fix cut over stratergy for go-live, but i as per requirement, i need to capture all historical costs and revenues (which were inccured in legacy system) into SAP. So i have very much confusion in this regards,kindly help me on this.

 

     Here the challenge is that, we need to calculate the RA (Cost based POC method) values in SAP based on cummulative Costs and Revenues both

Planned and Actuals.

 

I have read some blogs but still i have no clarity on bringing the historical Costs and Revenues into SAP. If any one can explain in detail that will be helpfull for me. Also please guide me how the WIP will be brought into project.

 

 

 

 

So please guide me how to achieve this.

 

 

 

 

Regards,

Rao.

Valuation Type not updated in CN25 Goods movement tab

$
0
0

Hi,

 

We are going to create project and assign material compnent to activity then we run MD51, Create PR,PO and GRN.

then i am trying to confiming activity thru CN25 valuation type field not update, every time i need to maintain manually.

 

so please suggest on this.....

 

 

 

regards,

siddu.

SAP PS Certification tips and tricks

$
0
0

Hello Gurus,

I am applying for SAP PS C_TPLM22_64 course certification from SAP directly with reference to my company. I have filled required documents given by SAP.

As per their confirmation mail , study material will not be provided by them. I just read from net about no of questions , negative marking , important topics.

I just wanted to know some tips and tricks ( basic) so as to appear for the exam. Also as per policy of SAP I can apply within 2 months only from the date of confirmation mail which I received yesterday.

As I working on SAP PS only , I just wanted to know that 2 month time period is sufficient for a working guy to appear for the exam ?

Sorry for the basic question. Hope you will reply.

 

Thanks and Regards

Raghav Puranik

Settlement by item

$
0
0

hello

 

I have an activity with POrder, and with 3 invoices posted to this PO and in effect to the activity.

The invoices are posted with the same cost element.

Activity is assigned to WBS and settlement rule of activity is settle 100% of cost to WBS.

So when I settle by CJ88 my activity to WBS I get only one item on the WBS level.

eg

Before settlement

900001 0010

CE               Amount

4100015      1000 $

4100015      2000$

4100015      1500$

 

After settlement

900001 0010

CE               Amount

4100015      1000 $

4100015      2000$

4100015      1500$

4100015     -4500$

 

WBS level

4100015 4500$

 

Is there any option to have 3 items after settlement on the WBS level? Like below:

 

After settlement

 

900001 0010

CE               Amount

4100015      1000 $

4100015      2000$

4100015      1500$

4100015      -1000 $

4100015      -2000$

4100015      -1500

 

WBS level

4100015      1000 $

4100015      2000$

4100015      1500$

 

 

 

Viewing all 2586 articles
Browse latest View live


<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>