Hi Everyone,
Please suggest on below two issues on the earliest.
1. My client requires Progress analysis at Activity level, but SKF tab not coming at activity level, I found SAP note 1733126, 19015666, 1376215 but while implementation , It is showing message - SAP Note does not contain valid Correction instructions. Could you please how SKF tab not coming at Activity level to plan quantity.
CJK2 also does the same work which i believe but getting message there -
Locks or problems have occurred / Network has activity account assignment.
2. Client wants SKF in planning for below purpose. how it can be done.
planning the work of an activity and entering the SKF’s( production rates) for the particular activity, the system will propose the duration for which this activity is planned. This is related to EC&O.
Pls suggest at the earliest.
Regards
Gaurav Ahuja