Quantcast
Channel: SCN : Discussion List - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 2586

SD- PS Integration query

$
0
0

Hi,

 

I am first time working for SD and PS integrated process kindly help me with my requirement

 

1. when client is excepting project there are multiple activities for what charges are different

 

e.g   XYZ is a project

 

and there are different activities like X, Y and Z

 

so client issue invoice some time separately or some times together for each activity. X is deliverable, Y and Z are non deliverable.

 

we can not name X,Y and Z as milestone as these are different activities which are going parallel.

 

can we create different line item in sales order for X,Y and Z?

 

can we assign different WBS element for each activity but in PS it should be considered as one project.


Viewing all articles
Browse latest Browse all 2586

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>