Hi,
I noticed it that all sub-objects such as WBS Elements and Network, Activities get released with the Project Definition Release and Save , but, if I add other WBS Elements and other networks to it, only the WBS Elements get REL status but Network is still in CRTD status.
I was earlier under impression that if a Project Definition is REL, all subordinate objects including Network and Activities too get a default status REL too, no matter even if they are added post Project release.
And surprisingly, the Project Definition system status was still REL and not PREL !!
Should the system not Release all associated networks/activities too ? And does it treat WBS Elements and Networks differently even when these are both supposedly part of Project System structure only.
Thanks for any help.