use "overhead key/costing sheet" in report painter/writer
Hi guru,I have the following questionMy customer wants a report where there are on the row the WBE and in colums actual costs. Now he wants three colums for actual costs, the first that has actual...
View ArticleData archival of PS project .
1) For Ps_Project there are many info sets provided. Which is most appropriate one to be used?2) Also when I execute my delete job even though if it’s successful Data is not deleted from PROJ...
View ArticleAdding Networks in a project via cj20n
Hi, I am creating a project via cj20n. however i am having problems when adding networks to my project. i can't add a network when i click the network overview button, the fields for the network are...
View ArticleResource Related Billing
When carrying out ECP and sales pricing for resource related billing through CJ20n for T&M we are getting EK01 in USD (Controlling area currency) even though we have configured ODP1 with...
View ArticleCJI4 doesn't show any value in certain version
Dear Gurus, Can you help me with my cases, I've already maintained CO version (OKEV) Integrated Planning and maintained in 3 version (version 0, 1, and 2) and in all fiscal years. I want to maintained...
View ArticleValidation for CoCode at WBS element
Hi All, I am writing a validation to have a identical company codes at level 2 and level 3 WBS element for particular project profile. But this validation does not work. Below is the validation....
View ArticleWhen Milestone confirm , the actual date issue.
HI, I have milestone under activity in project builder. First time, the milestone scheduled date is set by activity earliest Start date.Because I have not checked 'Offset to fin.' It means that we...
View ArticleCJ88 Settlement error!
Can anyone help with this. When running settlement in cj88, I get the error 'GL account does not exist in chart of accounts'. The cost element giving this error is currently created as a secondary...
View ArticleAutomatic generation of settlement rule not working for all wbs elements
Hello, Can anyone help with this. I have noticed that when I create and release me project and generate settlement rules, not all the WBS elements have their settlement rules generated. As such, when...
View ArticleValidation for WBS field Length
Dear All, I am using following Project coding mask T.00.XXX.000.000.00.00.0 Where Project code- T.00.XXX.000Level 1 WBS -T.00.XXX.000.000Level 2 WBS-T.00.XXX.000.000.00Level 3WBS-...
View ArticlePS Migration from 4.6C to 6.0
Hi All, We are on version 4.6C and are upgrading to 6.0. We have some open projects which we need to move to the new version. May I seek your help to understand what should be our approach to...
View Articleprofit indicator
Hi in the Completed methord of RA analysis the profit indicator is set to 'C', When the project is set to TECO and KKA2 is run, the profit indicator is coming as 'M' Sometimes 'O', Does the profit...
View ArticleAccess Control List
Dear Experts, My requirement is that:- While creating a PO/PR the user enters a WBS element .At presen anyone can use the WBS element and create PR/PO.They are not creain PR/PO by using PS but they...
View ArticlePurchase Requisition commitment for WBS
Hi! PS Gurus!There is one issue in my support project. While closing one WBS, the system gives an error that u201CThere is still Purchase Requisition commitment for WBSu2026.u201DBut when I checked...
View ArticleAggregation in Qty Proportionality
Our Client is using is QTY proportionality method for progress analysis.In this method, the aggregation of the POC is not happening to the superior level WBS in spite of maintaining the required SKFs...
View ArticleReactivate depriciation area of AUC
Hi PS guru's, We are facing problem in AUC which is getting created automatically while creating L-5 WBS element.User has deactivated all the depriciation area , and this AUC has been created on 2011,...
View ArticleCash Management (Cash Flow) in Project System
Hello experts, We are implementing PS for a construction company, the requirement is Cash Flow report from PS, now the issue is Funds Management has been activated and i have also...
View ArticleSettlement of plan values to FXA(AUC)
Hi All, When I try to do Plan settlements (CJ9E) I get the following message:Plan settlement only poss. to receiver categories CTR, BPR, PSG, ORD, WBSMessage no. KD083. It seems like PS does not allow...
View ArticleSD- PS Integration query
Hi, I am first time working for SD and PS integrated process kindly help me with my requirement 1. when client is excepting project there are multiple activities for what charges are different e.g...
View ArticleNetwork status is not changed to REL
Hi, I noticed it that all sub-objects such as WBS Elements and Network, Activities get released with the Project Definition Release and Save , but, if I add other WBS Elements and other networks to it,...
View Article